You know the room you need. A third bedroom, a primary suite on the ground floor, a kitchen that finally opens onto a family room. An addition is a different kind of project from a remodel, and that's harder to see from the driveway. A remodel works inside walls that already exist. An addition makes the house bigger, so the lot, the city, the old structure and the utilities each set limits or requirements, and the permit, the price and the calendar depend on what those turn out to be.
Five things decide most of it, and they're worth getting straight before you compare bids. (If you're still choosing between an addition and a separate unit in the yard, our ADU vs home addition guide covers that choice. This post assumes the addition is the plan.)
Cities limit how much house can sit on a lot. Setbacks keep the building a set distance from the property lines. Lot coverage caps how much of the ground the building can cover. Height limits and floor-area ratios (the total floor space allowed against the size of the lot) cap how big the house can get overall. The numbers differ from city to city, and sometimes from one zone to the next inside the same city. Many Bay Area lots were built out decades ago, so the room left over is often smaller than it looks from the back door. The lot often decides the plan before the design does.
Going up adds another layer in some cities. Palo Alto, for one, sends new second stories on single-family homes, and upper-story expansions over 150 square feet, through an extra review. The city's Single-Family Individual Review Guidelines judge how the addition looks from the street, how its height and mass compare with the neighbors', and where the new upstairs windows look into the next yard. A review like that can change the design and add weeks, so ask any builder you're considering whether your city has one.
The new walls need a foundation, and that foundation has to tie into the old one. The new roof has to meet the existing roofline, where the rafters, valleys and flashing all have to line up. An engineer checks that the weight of the new part has a path down to the ground, and that the old and new sections brace each other in an earthquake, because they won't move the same way when the ground does.
Your house has also been settling for decades, so it rarely sits where the original plans say it does. The engineer and the builder work from measurements of the house as it stands today. A second story is the same question turned upward: the walls and foundation under it were built to carry one floor, and sometimes they need strengthening to carry two. Whether they do is the engineer's call, and the answer can move the price a lot.
That makes this the part of a bid to read first. A bid that doesn't mention the foundation or the engineer hasn't priced it. Our home additions page covers the foundation, framing, roofline and utility work, and the inspection sequence.
More square feet means more to heat, cool, light and plumb, and the existing systems were sized for the house as it was.
The electrical panel is the common surprise. Some older Bay Area homes still have a 100 amp panel, and a new bedroom with its own heating and a bathroom can push it past what it can carry. The fix is a bigger panel, and sometimes the utility has to upgrade the service to the house first. That work runs on the utility's schedule, not the builder's, which is why the request goes in during design and not after construction starts.
The same capacity question applies to heating and cooling (the existing system may be too small for the added rooms) and to plumbing. A new bathroom needs a drain path, and in a house on a slab that can mean cutting the concrete to run it. California's energy code also generally applies to additions, so the permit set has to show insulation, windows and the heating system on paper before the city will review it.
An addition usually goes through two reviews, and the order matters. Planning looks at zoning: setbacks, coverage, height, and in some cities design or neighbor review. Then the building department's plan check reads the structural drawings, the energy forms and the rest of the permit set. Correction notes can come back from either one, and each round adds time. After the permit comes inspections in sequence: foundation, framing, rough mechanical work, insulation and final. Each stage generally has to pass before the next one can cover it up.
State law sets short review deadlines for ADUs. An addition generally isn't covered by them, so the city's own pace applies, and that pace changes from Palo Alto to San Mateo to Walnut Creek. A permit time you read in an ADU article doesn't carry over.
Ask for the calendar in three separate ranges: design, permit and construction, with what moves each one. The permit range depends on the city, so a builder can only estimate it, and a builder who gives you one number for all three is leaving out how uncertain the permit range is. Our process page walks through the order of the work from the first consultation to final approval.
Price per square foot is a starting point. Our ADU vs home addition guide puts a typical Bay Area addition at about $450 to $800 per square foot, which makes a 400 square foot addition roughly $180,000 to $320,000. The range is wide because an addition has costs a detached building doesn't: tying into the roof, matching the siding and trim, patching where new meets old, and working around a family still living in the house.
Two bids at the same price per square foot can leave very different things out. Ask for the bid in line items, so the foundation, the engineer, the panel, the heating and cooling, the permit and school fees and the finish allowances each sit on their own line. Our post on what to look for in a construction proposal covers how to read one.
Then there's the part nobody can see yet: what's behind the wall where the new section joins, and what's in the ground where the footing goes. In an older house, a cushion of 15 to 20 percent is a common planning figure, against the 5 percent many contractors pencil in. The better question for a builder isn't whether something will turn up. The better question is who pays when it does, and where the contract says so.
Here's how we handle it. Before you sign, we walk the house and the lot, name what we can see and what we think is likely, and you decide what goes in the budget. Anything we flag that you choose not to budget for is on you. A miss on our end is ours to pay for. Once the contract is signed, the price moves only for scope you authorize in writing, or for a flagged risk you chose not to fund. How you pay for the project is a separate conversation with a lender or tax adviser, and our financing page explains where it fits.
Each item above comes with one thing to ask your builder:
The additions we build start the same way whether the house is in Palo Alto, Redwood City or Walnut Creek: with a walk of the house and the lot. If you're weighing one, talk through your addition with us and we'll set up that walk.