ADU CONSTRUCTION TIMELINE: HOW LONG EACH OF THE 3 PHASES TAKES

ADU Construction / October 21, 2026 / Mendez & Son's Construction

A detached ADU in the Bay Area typically takes 9 to 14 months from the first architectural drawings to move-in day. That's the range we see on our own jobs, and it's longer than most homeowners guess when they first call. (A garage conversion usually runs shorter, 7 to 11 months, because the structure is already there.)

Plan Your ADU Timeline
Detached single-story backyard unit with white lap siding, a deck and a stone path, the main house next door
01 The Range

HOW LONG EACH OF THE 3 PHASES TAKES

The gap between 9 months and 14 matters when somebody's waiting on the unit: a parent who's selling their own house to move in, say, or rent you're counting on to start. And more of that gap sits before anyone breaks ground than after. Design and permitting together can swing by about four months from one project to the next, while construction, by comparison, swings by about two.

So how long does it take to build an ADU on your lot? Here's what happens in each phase, what pushes it toward the short end or the long end, and what you can ask about before you sign anything.

Drawings to move-in 9 to 14 months
Pencil sketches of a small house and a floor layout in a spiral notebook, a mechanical pencil resting on the page
02 Phase 1

SITE ASSESSMENT AND DESIGN: 4 TO 8 WEEKS

The three phases run in order: design, then permits, then construction. The request for the unit's electrical service usually needs to go in early and run alongside them, so it's covered under design.

Design starts with the lot, not the floor plan. Before anyone draws, the property gets measured and walked: where the setbacks fall, where the sewer and water lines run, where the electrical panel sits and how much room it has left, what the soil and the drainage look like. The architectural drawings come out of that, and they're the permit-ready construction documents the city reviews.

Toward 8 weeks

Unmade decisions usually push this phase toward eight weeks: a layout that changes after the engineer has started, a window package nobody's picked, an appliance list that keeps moving.

Toward 4 weeks

Knowing what the unit is for (a parent, a renter, a grown kid coming home) before the first line gets drawn pulls it back toward four.

Request the electrical service now

This is also the phase to request the electrical service. An ADU often needs more power than the main house's panel can spare, and the electric utility's side of that upgrade runs on its own schedule, separate from the city's permit review. (That's PG&E across most of the Bay Area, while Palo Alto runs its own utility.) Requested during design, it can move along while the plans sit at the city. Requested after framing, it can leave a finished unit waiting for power. The utility connections are also one of the lines most often missing from an ADU budget, and our ADU cost guide breaks down what they typically run.

Long-lead orders belong here too. Custom windows and doors can take weeks to arrive, and an order placed during design tends to show up about when the framing is ready for it.

03 Phase 2

PERMITS AND PLAN CHECK: 3 TO 6 MONTHS

Permitting is the phase with the least room to speed up once the plans are in. The city reviews the drawings, sends back corrections, then reviews the resubmittal. On our jobs, plan check alone commonly runs:

PLAN CHECK, IN WEEKS
Sunnyvale
6 to 10 weeks
Mountain View
6 to 12 weeks
Redwood City
6 to 12 weeks
Palo Alto
8 to 14 weeks
San Mateo
8 to 14 weeks
Walnut Creek
8 to 16 weeks
0481216
Each round of corrections: +2 to 4 weeks
A stack of architectural floor plan sheets, the kind of drawings a city reviews at plan check

Each round of corrections adds roughly 2 to 4 weeks on top of that. That's why the drawings from phase one matter so much. A clean, complete set of drawings, one that answers the reviewer's questions before they get asked, is the main lever on this phase.

Our ADU permit timeline by city goes deeper on how each of those cities runs its review, and our ADU permitting page covers what we handle with the city for you.

04 Phase 3

CONSTRUCTION: 4 TO 6 MONTHS

Construction on a standard detached ADU runs in roughly this order:

  1. 01Site prep and the foundation
  2. 02FramingInspection
  3. 03Rough-ins for the electrical, plumbing and mechanicalInspection
  4. 04Insulation, drywall and the exterior finishesInspection
  5. 05Interior finishes: cabinets, counters, tile, fixtures, paint
  6. 06Final inspection, the sign-off that lets someone live there

The city inspects at several of those stages, including the framing, the rough-ins and the insulation, and the next stage waits until the inspection passes. So inspection dates are one thing that moves this phase between four months and six.

Single-story wood wall framing going up on a concrete slab, with a neighboring house behind it

The other is what turns up in the ground, or what changes partway through. A sewer lateral in worse shape than anyone expected, soil that calls for a different foundation, a sink moved after the plumbing is roughed in. A late change like that seldom costs one trade one day. The plumber, the electrician, the drywaller and the painter can each have something to redo, and each of them has the next job already on the calendar.

05 The Walk

MUCH OF WHAT STRETCHES THE SCHEDULE IS VISIBLE BEFORE YOU SIGN

Look at the three phases side by side and the same handful of things keeps stretching the schedule:

  • ✓which city reviews the plans
  • ✓whether the panel can carry a second unit
  • ✓how far the new lines have to run to the street
  • ✓what the soil and the old sewer line look like

A contractor can see a lot of that on a walk of the property, before there's a contract.

That walk is where the timeline conversation belongs. When we walk a lot before writing a number, permit timing and the utility connection are two of the things we're looking at, along with whatever's likely under the yard. Each one we can see gets named before you sign, with a rough idea of what it does to the schedule and the budget, and you decide what to plan around. (You can read more about how we run a job from that walk to handoff.) After you sign, the schedule sits in Buildertrend next to the budget, so when an inspection date moves, you can see it on your phone the same as we do.

None of that makes a city review faster. But it does mean more of the swing in design and permitting is something you planned for, instead of something you found out about halfway through.

06 Your Next Steps

WHAT TO DO IN EACH PHASE

Here is what to settle or ask about in each phase:

01

Design

Settle what the unit is for before the first drawing, and ask whether the electrical service request goes in during design.

02

Permits

Ask which city reviews your plans, how many correction rounds the contractor usually sees there, and who answers them.

03

Construction

Lock the layout and the fixture list before framing starts, and ask how inspection dates show up on the schedule you'll see.

Plan Your ADU Timeline

WHERE DOES YOUR LOT FALL IN THE 9 TO 14 MONTHS?

Whether the unit's for a parent, a renter or the kids, the ADU construction we do across the Peninsula, the South Bay and the East Bay starts with a walk of the property. If you'd like a realistic idea of where your lot falls in that 9 to 14 months, plan your ADU timeline with us and we'll set up that walk.

Plan Your ADU Timeline See Our Design-Build Process

For ADU construction, garage conversions and home remodeling across the San Francisco Bay Area, visit https://mendezandsonsinc.com.

See our job-site photos as an ADU builder in the Bay Area on Instagram.